  • 7Ars Technica AI·9/7/2026research
    Fire exposes risks at $3.2B AI data center project

    A fire at the unfinished Lake Mariner data center in New York reportedly left firefighters without working alarms, suppression systems, or usable hydrant access, while safety documents were also unavailable. The site is part of a complex $3.2 billion AI data center buildout involving TeraWulf, Fluidstack, Google, and Anthropic-linked compute demand.